 Project Overview


 

Brookhole Weir

 

Client:

 

British Waterways / May Gurney

 

Duration:

 

4 Weeks

 

Completion:

 

April 2010

Sector: Water

 

Project Value:

 

£0.06M

Project Location: 

Cheshire

Huxley

Description:

-----------------------------------------------------------------------------------------------

Brookhole weir is located on the Shropshire Union Canal near Huxley in Cheshire.
The existing weir consisted of brickwork on sandstone and had been heavily eroded over the years.
The proposed works were to replace the weir with a new reinforced concrete weir. The weir crest was to be constructed 75mm below the existing weir crest level. The new weir however was to be furnished with a removeable weir crest extension with the capacity of raising the weir crest level by 75mm or 150mm. The weir was also to be furnished with a safe means of access, in the form of an aluminium walkway or bridge.
The removebale weir crest and the walkway were contractor designed by Hills Contractors Limited. The weir crest extension was achieved by the fixing of universal beams and channels to form stanchions on the wier crest and the installation of 75mm deep timber stop planks between. The timber planks were fixed in position by the insertion of steel pins through each stanchion and plank.
The works required the installation of a temporary dam around the weir which was achieved by portadam.
It was essential that the canal remained open to navigable traffic for the duration of the works.
The weir was accesed through adjacent farm land and all materials were transported in and out by land.
The works were completed on time, to budget and to a very high standard of workmanship.

-----------------------------------------------------------------------------------------------

Directions:

 



Generate Yahoo! driving directions to location

 

View on Map:



Find project location on map

 

Email to a Friend:



Forward details of this project by email

 

Project undertaken by Hills Contractors Limited.


Tel: 0121 568 7432

Fax: 0121 568 6394

Email: sales@hillscontractors.com

 

 










 Photo Gallery


Existing Weir Dewatered

[ 2010-04-14 ]

Existing Weir Dewatered

[ 2010-04-14 ]

Breaking Out Existing Weir

[ 2010-04-14 ]

Temporary Works

[ 2010-04-14 ]

Installation of Waterbar

[ 2010-04-14 ]

New Weir Crest

[ 2010-04-14 ]

Finished Weir & Access Platform

[ 2010-04-14 ]

Finished Weir & Access Platform

[ 2010-04-14 ]








 

Hills Contractors Limited. 

Unit 12, Holland Industrial Park, Bentley Road South, Wednesbury, West Midlands. WS 10 8LN.


© Copyright 2010 Hills Contractors Limited. All rights reserved.